So, here's what's gone on for the rest of August....
Days 15 and 16 (August 12-13)
  | 
| Looking to the northeast at the west side of the house. | 
  | 
| Looking to the west at the east side of the house. | 
Day 17 (August 14th)
  | 
| End of Day 17 - looking west at east side of house. | 
  | 
| Suki is very happy with the window height! | 
  | 
| We are standing in the doorway to the master bedroom. | 
Day 18 (August 15th)
  | 
| End of Day 18: looking west at east side of house. | 
Day 19 (August 16th)
  | 
| Today we had to pick a corbel design from these sketches. | 
So, today we had to pick a corbel design.  The need was immediate as the company in Las Cruces was going to cut them today and include them in a shipment coming tomorrow.  Eeep!  So, they emailed us this sketch of designs.  I had a really hard time envisioning what they would really look like based on these sketches.  We figured 3 of them would like be just fine, picked #2 and hoped for the best.
  | 
| Corbel. | 
Here's what design #2 looks like "in person".  We are pleased!  The wood you see in this picture is all Douglas fir. 
  | 
| End of Day 19: looking sort of south eastish from the patio. | 
Day 20 (August 19th)
The gorgeous beams for the great room went up and the eyebrows (overhangs for our south facing windows).
  | 
| Douglas fir beams in great room. | 
  | 
| Eyebrow decorative supports for window overhangs on south side. | 
Day 21 (August 20th)
  | 
| Sheathing going on and more eyebrows. | 
  | 
| Eyebrows here, but no sheathing on this end of house yet. | 
Day 23 (August 22nd)
  | 
| More sheathing up. | 
  | 
| Pine tongue & groove making up the great room ceiling. | 
  | 
| Tongue & groove again. | 
Day 24 (August 23rd)
  | 
| Tongue & groove in great room all installed. | 
  
  | 
| Our walk in shower! | 
So, that is it for August.
 